Ottawa’s transit boss delivered a positive update on the long-awaited light rail transit line Wednesday morning, indicating Rideau Transit Group is on track to deliver the system next month
Ottawa taxpayers won’t be on the hook for an estimated $34.4 million in costs related to the delayed opening of phase one LRT – assuming the city can get the light-rail builder to pay
Rideau Transit Group has not provided a new date to hand over the system, though the city has been told to expect work to finish by the second or third week of August
Ottawa’s light-rail transit line will not be ready by June 30 as promised due to issues with the trains, OC Transpo head John Manconi told Ottawa councillors Tuesday morning.
Rideau Transit Group has not achieved substantial completion on Ottawa’s light rail transit line, according to an independent certifier, but the city still expects to have the keys to the system by
While all 13 stations on the Confederation Line have occupancy permits, more work still needs to be done on the vehicles themselves before light rail is ready to roll, OC Transpo boss Joh
The consortium building the first phase of Ottawa’s light-rail transit system will miss its third handover deadline, with the system now expected to be delivered in the second quarter of
The head of the consortium constructing Ottawa’s light-rail transit line said Tuesday he’s “confident” the system will be ready to be handed over to the city on March 31, but the city’s t
Construction on phase one of the Confederation Line will indeed wrap up this quarter, but the date passengers can start riding Ottawa’s new light-rail transit line remains unknown.
Not even another delay in the launch of Ottawa’s $2.1-billion LRT system is enough to dampen the spirits of OC Transpo boss John Manconi when he talks about how the new line will benefit the local