Rideau Transit Group’s work on the Confederation Line LRT is officially complete
After four missed deadlines and more than six years of work, city staff and an independent certifier say Ottawa’s $2.1B LRT project is complete

Rideau Transit Group’s work on the Confederation Line LRT is officially complete
After four missed deadlines and more than six years of work, city staff and an independent certifier say Ottawa’s $2.1B LRT project is complete

Ottawa’s Confederation Line LRT to open on Sept. 14
Nearly 15 months after the Confederation Line was originally slated to be carrying passengers, Mayor Jim Watson made it official Friday: the east-west LRT route

RTG misses latest LRT handover date, but service still expected in September
Rideau Transit Group will not hand over the keys to Ottawa’s light-rail transit system as planned on Friday, but city staff remain confident riders will

City says LRT work ‘substantially complete,’ final testing to start this week
The city and builders Rideau Transit Group are now holding their collective breaths that the final testing hurdle goes off without a major hitch

Builder says work on Ottawa LRT complete, looks to enter final testing
Rideau Transit Group says it’s finished its work on Ottawa’s light-rail transit system and is ready to enter the final hurdle of testing

With trains delivered, RTG looks to clear final testing hurdle before LRT handover
Ottawa’s transit boss delivered a positive update on the long-awaited light rail transit line Wednesday morning, indicating Rideau Transit Group is on track to deliver

City says it expects to recoup all LRT delay costs from developers
Ottawa taxpayers won’t be on the hook for an estimated $34.4 million in costs related to the delayed opening of phase one LRT – assuming

Confederation Line LRT service to start in September: Watson
Rideau Transit Group has not provided a new date to hand over the system, though the city has been told to expect work to finish

Confederation Line will not be ready for handover by end of June
Ottawa’s light-rail transit line will not be ready by June 30 as promised due to issues with the trains, OC Transpo head John Manconi told

RTG’s work on Ottawa LRT not substantially complete: independent certifier
Rideau Transit Group has not achieved substantial completion on Ottawa’s light rail transit line, according to an independent certifier, but the city still expects to