Construction work on a pedestrian bridge over the Airport Parkway is scheduled to begin again on Wednesday, over two years after it was originally supposed to be finished.
Work first began on the bridge, intended to link Hunt Club Road with the South Keys shopping centre and the Transitway, in June 2011. Primary construction was supposed to be finished that fall, with landscaping and some other work set for May 2012.
But, after initial delays pushed construction into to the spring, concrete used in the construction failed to set properly, requiring much of bridge to be torn down.
OBJ360 (Sponsored)
Giving Guide: The Ottawa School of Art
What we do The Ottawa School of Art is a non-profit organization that offers a full range of specialized art courses for adults, teens and children in drawing, painting, photography,
A global research powerhouse – right here in Ottawa
Many in the region are unaware, that right here in Ottawa, we have a global research powerhouse. And it’s not a private company, a start up, or a LLC —
Work was suspended again in October over design concerns.
The bridge, which originally had a price tag of $7 million, is now expected to cost the city $11.65 million.
The fiasco triggered a third-party review of the project, which Mayor Jim Watson described as an “embarrassment.”