Construction work on a pedestrian bridge over the Airport Parkway is scheduled to begin again on Wednesday, over two years after it was originally supposed to be finished.
Work first began on the bridge, intended to link Hunt Club Road with the South Keys shopping centre and the Transitway, in June 2011. Primary construction was supposed to be finished that fall, with landscaping and some other work set for May 2012.
But, after initial delays pushed construction into to the spring, concrete used in the construction failed to set properly, requiring much of bridge to be torn down.
(Sponsored)

OCOBIA eyes Ottawa BIA expansion as it gears up for election year
Michelle Groulx says it’s not difficult to spot the Ottawa neighbourhoods with their own business improvement area (BIA). That’s because, she says, BIAs are a visual and experiential representation of

How shared goals at Tamarack Ottawa Race Weekend strengthen workplace culture
Across workplaces of all sizes and sectors, organizations are continuing to look for meaningful ways to bring people together. Team connection, employee well-being, and community impact are no longer separate
Work was suspended again in October over design concerns.
The bridge, which originally had a price tag of $7 million, is now expected to cost the city $11.65 million.
The fiasco triggered a third-party review of the project, which Mayor Jim Watson described as an “embarrassment.”