A construction crane working on Ottawa’s Confederation Line project toppled over Wednesday morning.
The crane was working at the eastern tunnel entry portal near the University of Ottawa lowering a cement mixer into the tunnel when it toppled over.
Rideau Transit Group spokesperson Kathryn Keyes said the Ministry of Labour is investigating, but they have a theory about what cause the crane to topple.
OBJ360 (Sponsored)
Last month Ottawa Salus launched “Opening Doors to Dignity,” a $5-million campaign to construct a 54-unit independent living building on Capilano Drive. Set to open in late 2025, this innovative
The Ottawa Hospital’s Campaign to Create Tomorrow enters important next phase
For Ginger Bertrand, some of her earliest childhood memories in Ottawa are centred around healthcare. “I grew up across the street from what was originally the General Hospital,” she explains,
“It became unstable, we suspect that probably it’s stabilizers were not deployed the way they’re supposed and it resulted in the crane tipping over.”
Keyes said work on that area of the project has stopped until the ministry’s investigation is complete, but the tunnel work is continuing further up the tracks.
“At that particular site work has stopped until the Ministry of Labour gives us the go ahead to proceed,” she said.
Keyes said when the ministry gives them the all clear they will remove the crane.