Anger, drama fuel meeting on mounting issues with Ottawa LRT

Ottawa city hall’s top bureaucrat has told elected officials that he’s ready to take the blame if councillors want someone’s head to roll over ongoing troubles with the city’s light-rail system.

Steve Kanellakos’ opening remarks at an emergency meeting of the city’s transit commission put into focus the level of anger directed at city hall over a new transit line that seemingly can’t run without any drama.

Kanellakos said no one overseeing the capital’s transit service predicted that the $2.1-billion system – funded by local, provincial and federal dollars – would face the number of problems it has.

OBJ360 (Sponsored)

“No one could anticipate that we would have to literally throw our plan into the waste can and come up with a new plan to be able to deliver services,” Kanellakos said during Thursday’s meeting.

“If you do believe that we have not done everything possible to improve this system, make this better … dismiss your city manager,” he added later. “Don’t take out the people that are killing themselves every day to try and fix this system and make it better.”

The ongoing problems have attracted attention from outside the capital from cities eyeing similar LRT systems, or, in the case of Metrolinx in the Toronto area, purchasing the same cars made by French-based multinational Alstom.

Service has been repeatedly brought to a halt by problems with stuck doors on the fleet of trains and failing onboard computers.

More recently, trains have been taken out of service because the wheels have flat spots, an overhead power cable snapped, and rail switches have gotten stuck in a heavy snowfall – apparently because the private maintenance company made a mistake with staffing.

Several problems popping up in recent days, as snow and deep cold took hold in Ottawa for the first time this winter, were identified as deficiencies during winter testing last year.

The switches will be tested again, along with maintenance plans, in coming days. The forecast for the weekend calls for the same amount of snow that has caused problems before.

Shortages of trains on the Confederation Line have persisted all week, forcing OC Transpo to run extra buses to handle the demand.

The company contracted to maintain the system, Rideau Transit Maintenance, said it is bringing in a team of outside rail experts to help after acknowledging a lack of in-house expertise.

It is also looking at ways to keep the switches clear, such as boosting heaters along the rails to melt snow and having more workers bearing blow torches out in the storms.

The city’s transit commission also heard that some other issues appear to have been resolved, such as a serious software glitch in onboard computers. Riders are also now appearing to heed calls to stop blocking train doors.

But members of the commission are also expressing concern about what the slip-ups on the Confederation Line might mean for the next phase of light-rail work, which is supposed to extend coverage to other parts of the city.

Get our email newsletters

Get up-to-date news about the companies, people and issues that impact businesses in Ottawa and beyond.

By signing up you agree to our Terms of Use and Privacy Policy. You may unsubscribe at any time.

Sponsored

Sponsored

EVENT ALERT: Mayor's Breakfast with Ontario Finance Minister on Wednesday, Dec. 4 @ City Hall