Construction deadline
The contract between the City of Ottawa and the Rideau Transit Group (RTG) established May 24, 2018 as the date the city officially takes ownership of the O-Train Confederation Line. This is known as the “Revenue Service Availability” date. RTG still believes it will meet this deadline. If it does not, it will lose out on some monthly service payments, outlined in the agreement.
Opening date unknown
The Revenue Service Availability date is not the same as the date the LRT will be open to the public. Once the city takes ownership of the line, it will begin conducting a series of tests and safety inspections of all operational elements before it opens to the public, including checking trackwork, vehicles, communications systems, tunnel ventilation and signals. City staff will not know for sure when the LRT will open to the public until the end of 2017.
Safety issues
The RTG has received approximately 150 recent orders from the Ministry of Labour, including orders to improve lighting, and address problems with site housekeeping and washroom facilities, according to the report. RTG says it has resolved the issues. The Ministry of Labour ordered RTG to stop work at the site of the toppled crane on April 26 for two days, but it has since restarted. The gas main break on Queen Street on May 2 is still under investigation.
OBJ360 (Sponsored)
The value of an Algonquin College degree: Experiential learning, taught by industry experts
Zaahra Mehsen was three years into a biology degree at a local university when she realized she wanted to take a different path. “I realized that it’s not my thing,”
The Ottawa Hospital’s Campaign to Create Tomorrow enters important next phase
For Ginger Bertrand, some of her earliest childhood memories in Ottawa are centred around healthcare. “I grew up across the street from what was originally the General Hospital,” she explains,
2017 Canada Day Celebrations
The project agreement included a requirement that city streets between the east and west downtown entrances of the Confederation Line be restored to pre-construction configuration before Canada Day 2017. That is not going to happen because of delays connected to the Rideau sinkhole. Surface work will continue well into the summer, but the RTG will cease construction on Rideau Street on Canada Day to try to limit disruptions to the public.
Completed work
Nine vehicles have been fully assembled and are in various stages of testing; 142 of 323 poles for the overhead electrical line have been installed. Excavation work is done for the last section of the tunnel west of Rideau station, the west portal ramp and the entrance to the Parliament East station; excavation work continues on the east portal ramp. Servicing work at Tunney’s Pasture Station is almost done.
This story originally appeared in Metro News.