Nearly 15 months after the Confederation Line was originally slated to be carrying passengers, Mayor Jim Watson made it official Friday: the east-west LRT route will be ready to roll on Saturday,…
Rideau Transit Group will not hand over the keys to Ottawa’s light-rail transit system as planned on Friday, but city staff remain confident riders will be on the trains by the end of September
The city and builders Rideau Transit Group are now holding their collective breaths that the final testing hurdle goes off without a major hitch
Rideau Transit Group says it’s finished its work on Ottawa’s light-rail transit system and is ready to enter the final hurdle of testing
Ottawa’s transit boss delivered a positive update on the long-awaited light rail transit line Wednesday morning, indicating Rideau Transit Group is on track to deliver the system next month
Beginning Monday morning, Ottawa Police Services, city by-law officers and transportation officials will take to the streets to implement additional traffic control measures
Ottawa’s light-rail transit line will not be ready by June 30 as promised due to issues with the trains, OC Transpo head John Manconi told Ottawa councillors Tuesday morning.
Rideau Transit Group has not achieved substantial completion on Ottawa’s light rail transit line, according to an independent certifier, but the city still expects to have the keys to the system by
While all 13 stations on the Confederation Line have occupancy permits, more work still needs to be done on the vehicles themselves before light rail is ready to roll, OC Transpo boss Joh
The consortium building the first phase of Ottawa’s light-rail transit system will miss its third handover deadline, with the system now expected to be delivered in the second quarter of