The consortium building the first phase of Ottawa’s light-rail transit system will miss its third handover deadline, with the system now expected to be delivered in the second quarter of
The head of the consortium constructing Ottawa’s light-rail transit line said Tuesday he’s “confident” the system will be ready to be handed over to the city on March 31, but the city’s t
Construction on phase one of the Confederation Line will indeed wrap up this quarter, but the date passengers can start riding Ottawa’s new light-rail transit line remains unknown.
Not even another delay in the launch of Ottawa’s $2.1-billion LRT system is enough to dampen the spirits of OC Transpo boss John Manconi when he talks about how the new line will benefit the local
Ottawa’s light rail system will not be ready by the Nov. 2 handover date and trains aren’t expected to start carrying passengers until 2019, city staff announced Monday morning.
Ottawa’s transit boss John Manconi updated councilors on Confederation Line construction this week with the aid of a city-owned drone.
Ottawa’s light-rail transit line will open by the end of November, almost six months after the original date the city was to take possession of the system, Mayor Jim Watson announced today.
OC Transpo revenues are down over the first half of 2017, as the transit agency deals with the financial impacts of higher-than-average lawsuit settlements and declining ridership rates.
With a task force working on a bid to bring Amazon’s second headquarters to the capital, Ottawa’s top planning guru said Tuesday it’s time for the city to step up its game when it comes to going af
The City and its LRT contractor are defending the safety record of the Confederation Line, as the president of the city's labour council raises concerns the project is being rushed.